Notes and Actions from the WP4 Kick-off meeting 

1 March 2017

We had 2 WP4 meetings and a joint meeting with WP3 after lunch. The main points and actions were:

Network level Actions

  • Make a list of network level tests – which protocol stack and tool (we already have basic agreement)
  • Agree a set of data moving tools gridftp, bbcp, jive5ab (uses udt), aspera access from AARNet, S3-like REST, BitTorrent (for ceph storage)
  • Start defining European sites for tests Onsala, Jodrell, ASTRON/SARA, Julich, Bologna
People noted the AARNet-GEANT 10Gigs
 

Storage level

Input from RAL (STFC) the LHC Teir1 in UK on what is now possible using ceph and I swift.
They will use gridftp to move data but aiming for S,3 like AARNet 3 site replication  storage and data moving are not separated.
Julich and RAL (new partner) will work together.


Replica manager level

The who, what, why, level of detail for the SKA “data replica manager” most unclear.
Agreement it needs to be SKA wide and users should not need to know where the data files are.

Data placement:              

Again details of SKA requirements are quite uncertain

  • Agree the SDP will be in charge of scheduling and sending the data out of the telescopes   
  • Agree Telescopes will only send the data out once – cost of submarine cable
  • Agree that for the European ESDC the data products will be distributed across the sites that form the ESDC
  • NOT clear that all data products will go to one regional site and then be re-transmitted
  • NOT clear that some products will go to individual regional centres and all users will be able to send compute jobs to all sites to see all the data
  • Suggestion that ESDC will have all data from both Telescopes
 

Software and Hardware Platforms

                Some think it will all be based on OpenStack – and OpenStack will rush to help SKA
                Others think SKA will have to invest heavy manpower in o OpenStack
                Agreement that OpenStack will have its own agenda – need not be in phase with what SKA needs

                Some sites use bare linux for data transfer nodes
                Others use Containers
 

WP3-WP4 joint milestones etc

               General agreement that the timing is about right
               Willingness to work together – that’s good
 

WP4 internal communications Conclusions

               AARNet will give us access to zoom – excellent
               Slides to go on the meeting page indico
               Agreement to have VC/telcon 1 per month – day & time to be fixed
               Agreement to have extended VC to discuss bit & bytes of results every 3 months
               Agree to have ½ day workshop at each AENEAS F2F which will be every 6 months.
 

Manpower

               We would like to add Tim Rayner to the AARNet team (have a look at the slides for the others)
              All to confirm their participation and FTE in the WP4 Tasks
 

Tasks

  • T4.1 and T4.4 PoC continue the setting up and work in progress – draft technical notes on the results.
  • T4.2 draft questions to get the technical info needed, introductions with WP2 made so we work with them on whick sites to approach and when
  • T4.3 Need a person to start on DMZ





There are minutes attached to this event. Show them.
    • 10:15 10:20
      Welcome & Agenda bashing 5m
      Speaker: Richard Hughes-Jones
    • 10:20 10:35
      Round Table Introductions 15m
      Who I am, My institute & Group, My work interests & expertise
      Speaker: All
    • 10:35 10:55
      Plans and Discussion of the WP4 Tasks 20m
      Outline of how the Tasks support the Statement of Work Discussion of the Timelines Technical Notes, Milestones & Deliverables Interactions and inter-dependencies with other WP
      Speaker: All
      Slides
    • 10:55 11:15
      Some Current Work
      Convener: Richard Hughes-Jones
      • 10:55
        Work at Onsala on protocols & data transfers 5m
        Speaker: Simon Casey
        Slides
      • 11:00
        Work at Juelich on dCache for LOFAR 5m
        Speaker: Oleg Tsigenov
        Slides
      • 11:05
        Work at Trieste on Data Transfer Nodes and Physics data transfers 5m
        Speaker: Riccardo Smareglia
        Slides
      • 11:10
        Tests of 100Gigabit Ethernet on PCs & long haul to AARNet 5m
        Speaker: Richard Hughes-Jones
        Slides
    • 11:15 11:30
      Coffee Break 15m
    • 11:30 11:50
      The work within each Task 20m
      Speakers: Mauro Nanni, Richard Hughes-Jones, Simon Casey
    • 11:50 12:10
      Agreement Linking People to Tasks 20m
      Speaker: ALL
    • 12:10 12:15
      Timescales & Interaction with WP3 5m
      Speaker: All
    • 12:15 12:30
      Functioning of WP4
      Convener: Richard Hughes-Jones
      • 12:15
        Initial Work Steps 5m
        Speaker: All
      • 12:20
        Identify Sites and Work in Progress 5m
      • 12:25
        Collaboration Tools 5m
        Speaker: Richard Hughes-Jones
    • 12:30 13:30
      Lunch Break 1h
    • 13:30 14:30
      WP3 and WP4 Joint Workshop
      • 13:30
        Sketch of WP3 Plans 15m
      • 13:45
        Sketch of WP4 Plans 15m
      • 14:00
        Discussions Covering 30m
        Time Scales Joint Milestones & Deliverables Data locality A Data Replica Manager for SKA